On this page, you can gain an insight into the improvements we are making to our campus and keep up-to-date with the progress of the works.
October 2022:
The new building will house our T-level Healthcare Science students and is nearly complete.
September 2022:
Redevelopment works have started on our new Plumbing and Gas Engineering facility for our students and apprentices.
May 2022:
The steelwork has been erected.
22 February 2022:
Concrete has been poured for the foundations of the building.
27 January 2022:
Construction works have started on a new two-storey building at our Healthcare Campus. The building will house specialist facilities for our T-level Healthcare Science students
13 December 2021:
The demolition of the former clubhouse at our Healthcare Campus is complete. The demolition will make way for a new two storey building that will house specialist facilities for our T-level Healthcare Science students.
Within the building will be several advanced multi-functional teaching spaces, including two specialist science laboratories, breakout spaces with innovative technology allowing for independent learning, and four classrooms equipped with the latest mobile devices.
26 October 2021:
Our Electro Technical Engineering T-level workshop is complete! This resource will allow our Electro Technical Engineering T-level students access to state-of-the-art real-life working environment bays and collaboration screens.
26 October 2021:
Our Digital T-level Lab and Studio are now in use! These facilities provide our Digital T-level students with a technical environment, enabling them to work on live servers and switching cabinets. They can also hone their skills on a range of processes, including Operating System installation and copper/fibre cabling.
13 September 2021:
The new Learner Support Hub on the 4th Floor Balliol building is nearly complete.
4 August 2021:
A £60,000 investment will enhance the facilities available to our students who access Learner Support. The new facility, located on the 4th floor of the Balliol building, will be a safe and welcoming space for students to access, study and achieve.
4 August 2021:
£50,000 is being invested to provide new classroom facilities for our T-level courses. The rooms will be based on our recently established teaching practices and will provide a modern look with flexible furnishing, and our new collaboration walls.
4 August 2021:
A large investment is being made to provide our Digital T-level students with a technical environment, enabling them to work on live servers and switching cabinets. They will be able to hone their skills on a range of processes, including Operating System installation and copper/fibre cabling. To complement this facility, we will also be commissioning a flexible learning room where T-level students will be able to practice coding and project development.
4 August 2021:
A significant investment in this facility will provide a new resource for our Electro Technical Engineering T-level students, including 15 state-of-the-art real-life working environment bays and collaboration screens.
7 April 2021:
The room refurbishment works of 8 rooms in the Balliol building and Lifestyle Fitness building are now complete. View the rooms with our 360° images. If you have a VR headset, you can view them in Virtual Reality.
3 March 2021:
The room refurbishment works in the Port Academy Liverpool building are now complete. View the rooms with our 360° images. If you have a VR headset, you can view them in Virtual Reality.
5 February 2021:
An update from Contractor Caolan on the ‘A’ and ‘T’ rooms at the end of week 4.
5 February 2021:
An update from Contractor Caolan on the ‘A’ and ‘T’ rooms at the end of week 4.
8 February 2021:
A timelapse video showing the progress of the ‘A’ and ‘T’ rooms.
1 February 2021:
An update from Contractor Caolan on the ‘A’ and ‘T’ rooms at the end of week 3.
25 January 2021:
An insight from Contractor Caolan on the progress of the ‘A’ and ‘T’ rooms.
21 January 2021:
A timelapse video showing the progress of the ‘A’ and ‘T’ rooms.
11 January 2021:
Work begins on ‘A’ and ‘T’ rooms. The photos below show the rooms on the first day of the refurbishments.
19 February 2021:
Work has started on installing 350 solar panels to the roof of our Exeter Road wing. When ready, they’ll provide us with 125kW of green energy.
21 January 2021:
Work replacing the roof of the Exeter Road part of the Balliol building is nearly complete.
12 December 2020:
Work starts on replacing the roof of the Exeter Road part of the Balliol building. This part of the building includes Hairdressing, Beauty and Media Make Up and 14-16 College departments.